This website uses cookies to enable essential functions like the user login and sessions. We also use cookies and third-party tools to improve your surfing experience on preplounge.com. You can choose to activate only essential cookies or all cookies. You can always change your preference in the cookie and privacy settings. This link can also be found in the footer of the site. If you need more information, please visit our privacy policy.

Data processing in the USA: By clicking on "I accept", you also consent, in accordance with article 49 paragraph 1 sentence 1 lit. GDPR, to your data being processed in the USA (by Google LLC, Facebook Inc., LinkedIn Inc., Stripe, Paypal).

Manage settings individually I accept
expert
Expert with best answer

Francesco

100% Recommendation Rate

3,546 Meetings

18,842 Q&A Upvotes

USD 479 / Coaching

3

NPV /WAAC ?

Hello 

I come from a technical background, PhD in Engineering not MBA. I have a few questions about the NPV and I appreciate it if someone can clarify the following. 

1- Can someone please explain what is expected from advanced degree candidates to know about NPV during a case interview? every time I look it up or come across a case using NPV, they use a different approximation/method to calculate the NPV. It is becoming very confusing to me. 

A Few NPV equations that I came accross are:

NPV = -Initial Investment + (Future Value of Money/Discount Rate) 

NPV = Future Value of Money / Discount Rate 

 (usually Future Value of Money = Revenues - ongoing costs) - I think not sure!

- How you would interpret an NPV value?

2- There is a case in which we determine the following(the first half is all about determining the R and C as follows: 

- Revenues  = 928 M$ 

- Costs = 574M $

- Profits  = R -C = 354M $ 

Then there is this given which I totally did not understand (no clairification as to what it means): 

- Time value of money: 6 year lag for receipt of revenue 

to Determine the NPV they used WAAC (I have no idea what is this): 

Using the “Rule of 72,” we know that 72/rate of return means the number of years to double our money. With a six year lag and a 12% WACC, we know that all future cash flows must be halved 

$354/2 = $177M in present value (NPV)

clearly the 12% is 72/6 (lag years) 

Can someone please explain what is WAAC? Why NPV is halved? 

Hello 

I come from a technical background, PhD in Engineering not MBA. I have a few questions about the NPV and I appreciate it if someone can clarify the following. 

1- Can someone please explain what is expected from advanced degree candidates to know about NPV during a case interview? every time I look it up or come across a case using NPV, they use a different approximation/method to calculate the NPV. It is becoming very confusing to me. 

A Few NPV equations that I came accross are:

NPV = -Initial Investment + (Future Value of Money/Discount Rate) 

NPV = Future Value of Money / Discount Rate 

 (usually Future Value of Money = Revenues - ongoing costs) - I think not sure!

- How you would interpret an NPV value?

2- There is a case in which we determine the following(the first half is all about determining the R and C as follows: 

- Revenues  = 928 M$ 

- Costs = 574M $

- Profits  = R -C = 354M $ 

Then there is this given which I totally did not understand (no clairification as to what it means): 

- Time value of money: 6 year lag for receipt of revenue 

to Determine the NPV they used WAAC (I have no idea what is this): 

Using the “Rule of 72,” we know that 72/rate of return means the number of years to double our money. With a six year lag and a 12% WACC, we know that all future cash flows must be halved 

$354/2 = $177M in present value (NPV)

clearly the 12% is 72/6 (lag years) 

Can someone please explain what is WAAC? Why NPV is halved? 

(edited)

3 answers

  • Upvotes
  • Date ascending
  • Date descending
Best Answer
Book a coaching with Francesco

100% Recommendation Rate

3,546 Meetings

18,842 Q&A Upvotes

USD 479 / Coaching

Hi there,

Several questions ;) Let me go one by one.

1) NPV

The correct NPV formula closer to what you reported is:

NPV = -Initial Investment + (FCF/Discount Rate) 

Where FCF= Free cash flow of the project generated in one year (I guess that’s what you mean by Future Value of Money). Note that this formula assumes that (i) every year you will generate the same FCF and (ii) you will generate FCF forever with that project.

2) RULE OF 72

With the Rule of 72 you can calculate the time to double for a variable. The formula is:

Time to double = 72/r

Where r=discount rate*100 (so if the discount rate is say 15%, r=15).

3) WACC

From a theoretical point of view, the discount rate is normally approximated with the WACC of the company (Weighted Average Cost of Capital), which can be computed as follows:

WACC = Re x E/V + Rd x (1 - corporate tax rate) x D/V.

where:

Re= Cost of Equity

Rd= Cost of Debt

E= Equity

D= Debt

V= Total Value (E+D)

In practical terms, this is normally assumed to be 5% or 10% for simplicity in a case.

4) CASE QUESTION

I guess what they meant was that profits, not revenues, are going to be received in 6 years.

Given the WACC is 12%, if you apply the rule of 72 using the WACC as the discount rate, you will find that the returns of the project will double indeed in exactly 6 years (72/12=6 – see formula above).

So this means that if you have X in year zero and grow by 12% per year, this will be worth 2X in 6 years. Given in this case you have 354M in 6 years, 354M = 2X, so X (value today of that return) is 177M.

---

For more information on the other variables, you can refer to the following answer that goes more into detail:

https://www.preplounge.com/en/consulting-forum/case-net-present-value-calculations-325

Hope this helps,

Francesco

Hi there,

Several questions ;) Let me go one by one.

1) NPV

The correct NPV formula closer to what you reported is:

NPV = -Initial Investment + (FCF/Discount Rate) 

Where FCF= Free cash flow of the project generated in one year (I guess that’s what you mean by Future Value of Money). Note that this formula assumes that (i) every year you will generate the same FCF and (ii) you will generate FCF forever with that project.

2) RULE OF 72

With the Rule of 72 you can calculate the time to double for a variable. The formula is:

Time to double = 72/r

Where r=discount rate*100 (so if the discount rate is say 15%, r=15).

3) WACC

From a theoretical point of view, the discount rate is normally approximated with the WACC of the company (Weighted Average Cost of Capital), which can be computed as follows:

WACC = Re x E/V + Rd x (1 - corporate tax rate) x D/V.

where:

Re= Cost of Equity

Rd= Cost of Debt

E= Equity

D= Debt

V= Total Value (E+D)

In practical terms, this is normally assumed to be 5% or 10% for simplicity in a case.

4) CASE QUESTION

I guess what they meant was that profits, not revenues, are going to be received in 6 years.

Given the WACC is 12%, if you apply the rule of 72 using the WACC as the discount rate, you will find that the returns of the project will double indeed in exactly 6 years (72/12=6 – see formula above).

So this means that if you have X in year zero and grow by 12% per year, this will be worth 2X in 6 years. Given in this case you have 354M in 6 years, 354M = 2X, so X (value today of that return) is 177M.

---

For more information on the other variables, you can refer to the following answer that goes more into detail:

https://www.preplounge.com/en/consulting-forum/case-net-present-value-calculations-325

Hope this helps,

Francesco

Book a coaching with Agrim

100% Recommendation Rate

1 Meetings

66 Q&A Upvotes

USD 149 / Coaching

Hi Anon,

1. Discount rate / WACC

This is the rate at which money changes its value per year. In common life we see this manifested in the form of interest "rate" on your mortgage, or inflation "rate" in the economy, etc. If you loan your friend $100 today and ask them to return it back after 1 year with 10% interest, they will have to pay you back $110. In this deal the 10% interest rate is the discount rate.

WACC [Weighted Average Cost of Capital] - for all intents and purposes is the blended discount rate for a business transaction. Just take it and forget it. You don't need to worry about the specifics - best to refer to Investopedia for that.

2. Rule of 72

This is a short-cut / hack to get to basic time-value-of-money calculations. If you invest $1000 today in an index fund that gives you 10% per year returns - your $1000 will double after Z years - where Z = 72/10 = ~7 years. The values will be as follows:

  • Year 1: $1000
  • Year 2: $1100
  • Year 3: $1210
  • Year 4: $1331
  • Year 5: $1464
  • Year 6: $1611
  • Year 7: $1772
  • Year 8: $1949 (7 years after year 1)

This also works from the future to the present. If you would be inheriting $2000 in year 8 - it would be worth $1000 in year 1 (assuming the same 10% discount rate).

3. NPV

In theory one can write:

NPV = sum of present values of all future cash flows

Lets break that down a bit:

  • Cash flow in year 1 is the initial investment. Let it be X. Since X is in the present, its present value is also X. Also, since X is an investment/expenditure, lets denote it by -X.
  • Cash flow in year 2 is C. The present value of C = C/(1 + discount rate). So if the assumed discount rate if 10%, the present value will be = C/1.1
  • Cash flow in year 3 is C. The present value of C = C/(1 + discount rate)^2. The power is because the cash flow is 2 years in the future. So if the assumed discount rate if 10%, the present value will be = C/1.21

You will realise this is an infinite geometric progression starting from year 2. If you go through the infinite GP formula, you will realise that the sum of the present value of all the cash flows from year 2 onwards is = C/(discount rate)

Hence, the final formula will look like the following:

NPV = -X + C/r

4. 6-year lag

In the above example we saw that the investment in year 1 started bearing fruit from year 2 onwards. In reality, the projects may take longer than 1 year to setup (in this case 6 years). But, when the project does start bearing fruit - it will give C = 354M every year. Now going by the above concept we will have the following:

  • Cash flow in year 1 is the initial investment. Let it be X.
  • Cash flow in year 2/3/4/5/6 is zero (since the project is being setup)
  • Cash flow in year 7 onwards is 354M. As we discussed above, you need to find the present value of this 354M. Given that discount rate is 12%, 354M in year 7 will be worth 354/(1+12%)^6 today. Which will be roughly half of 354M. This is also a demonstration of the rule of 72.

Hope this helps!

Hi Anon,

1. Discount rate / WACC

This is the rate at which money changes its value per year. In common life we see this manifested in the form of interest "rate" on your mortgage, or inflation "rate" in the economy, etc. If you loan your friend $100 today and ask them to return it back after 1 year with 10% interest, they will have to pay you back $110. In this deal the 10% interest rate is the discount rate.

WACC [Weighted Average Cost of Capital] - for all intents and purposes is the blended discount rate for a business transaction. Just take it and forget it. You don't need to worry about the specifics - best to refer to Investopedia for that.

2. Rule of 72

This is a short-cut / hack to get to basic time-value-of-money calculations. If you invest $1000 today in an index fund that gives you 10% per year returns - your $1000 will double after Z years - where Z = 72/10 = ~7 years. The values will be as follows:

  • Year 1: $1000
  • Year 2: $1100
  • Year 3: $1210
  • Year 4: $1331
  • Year 5: $1464
  • Year 6: $1611
  • Year 7: $1772
  • Year 8: $1949 (7 years after year 1)

This also works from the future to the present. If you would be inheriting $2000 in year 8 - it would be worth $1000 in year 1 (assuming the same 10% discount rate).

3. NPV

In theory one can write:

NPV = sum of present values of all future cash flows

Lets break that down a bit:

  • Cash flow in year 1 is the initial investment. Let it be X. Since X is in the present, its present value is also X. Also, since X is an investment/expenditure, lets denote it by -X.
  • Cash flow in year 2 is C. The present value of C = C/(1 + discount rate). So if the assumed discount rate if 10%, the present value will be = C/1.1
  • Cash flow in year 3 is C. The present value of C = C/(1 + discount rate)^2. The power is because the cash flow is 2 years in the future. So if the assumed discount rate if 10%, the present value will be = C/1.21

You will realise this is an infinite geometric progression starting from year 2. If you go through the infinite GP formula, you will realise that the sum of the present value of all the cash flows from year 2 onwards is = C/(discount rate)

Hence, the final formula will look like the following:

NPV = -X + C/r

4. 6-year lag

In the above example we saw that the investment in year 1 started bearing fruit from year 2 onwards. In reality, the projects may take longer than 1 year to setup (in this case 6 years). But, when the project does start bearing fruit - it will give C = 354M every year. Now going by the above concept we will have the following:

  • Cash flow in year 1 is the initial investment. Let it be X.
  • Cash flow in year 2/3/4/5/6 is zero (since the project is being setup)
  • Cash flow in year 7 onwards is 354M. As we discussed above, you need to find the present value of this 354M. Given that discount rate is 12%, 354M in year 7 will be worth 354/(1+12%)^6 today. Which will be roughly half of 354M. This is also a demonstration of the rule of 72.

Hope this helps!

(edited)

Book a coaching with Antonello

98% Recommendation Rate

177 Meetings

6,967 Q&A Upvotes

USD 219 / Coaching

Related case(s)

Bain case: Asian lubricants producer

Solved 169.2k times
Bain case: Asian lubricants producer LubricantsCo, a very successful Asian premium producer of lubricants in their native region, would like to further increase their revenue and profit. The product range ranges from lubricants in the automotive sector (e.g. motor and gear oil) to industrial applications (e.g. fats, heavy-duty oils). According to preliminary examinations, further growth potentials in the Asian core market are rather limited. Thus, LubricantsCo would like to investigate options to internationalize in the passenger car business – also outside the premium segment which is given priority. Therefore, your consulting firm was instructed to elaborate a market entry strategy for the European market.  
4.6 5 29725
| Rating: (4.6 / 5.0)

LubricantsCo, a very successful Asian premium producer of lubricants in their native region, would like to further increase their revenue and profit. The product range ranges from lubricants in the automotive sector (e.g. motor and gear oil) to industrial applications (e.g. fats, heavy-duty oils). ... Open whole case

Bain Case: Old Winery

Solved 73.5k times
Bain Case: Old Winery You have inherited the “Old Winery” from your grandfather, a winery that has been family-owned for five generations and can be dated back to the 16th century. Half of the eleven hectares are used to grow white grapes, the other half to grow red grapes. They are grown in a conventional way, i.e. they are not organically farmed and certified. The vine stocks are in a good condition regarding age and care. Overall, the only ¼ of the harvest is made into wine by the winery itself; the rest is sold. Your grandfather never wanted to change the image of the winery and left the managerial and administrative task to a young and energetic wine-maker. Due to the not so well-known brand, the demand for the “Old Winery” wine is currently rather low. You do not intent to run the winery operatively, given your limited knowledge of winemaking, but find the idea of owning a winery exciting. Your plan is to give the winery some fresh impetus.
4.4 5 1952
| Rating: (4.4 / 5.0)

You have inherited the “Old Winery” from your grandfather, a winery that has been family-owned for five generations and can be dated back to the 16th century. Half of the eleven hectares are used to grow white grapes, the other half to grow red grapes. They are grown in a conventional way, i.e. the ... Open whole case

McKinsey Questions

Solved 40.4k times
McKinsey Questions Tell me of a situation where you had an opinion and no one seemed to agree with you. What was your goal when you decided to join university / work / clubs / a sports team? Did you have a goal that you were not able to reach? What did you do? What do you want to be remembered for and how are you achieving it? What is your typical way of dealing with conflict?
4.5 5 865
| Rating: (4.5 / 5.0) |
Difficulty: Intermediate | Style: Fit Interview | Topics: Personal fit

Tell me of a situation where you had an opinion and no one seemed to agree with you. What was your goal when you decided to join university / work / clubs / a sports team? Did you have a goal that you were not able to reach? What did you do? What do you want to be remembered for and how are you ... Open whole case

Smart Meters

Solved 31.8k times
Smart Meters The municipal utility Hamburg Energized is a local energy retail (power and gas) and distribution grid company active in the city of Hamburg. The majority of shares of Hamburg Energized is held by the city itself. As the distribution system operator of Hamburg, Hamburg Energized is responsible for the operations and maintenance of the gas and electricity grid on customer level. In the course of the energy transition in Germany, the responsible board member for the technical grid operations, Jan Bremer, thinks about deploying Smart Meters in the gas and electricity grid. He approaches you with the request to conduct a feasibility analysis and to give a clear recommendation whether or not Hamburg Energized should use Smart Meters in its gas and electricity grid in the future.
4.4 5 699
| Rating: (4.4 / 5.0)

The municipal utility Hamburg Energized is a local energy retail (power and gas) and distribution grid company active in the city of Hamburg. The majority of shares of Hamburg Energized is held by the city itself. As the distribution system operator of Hamburg, Hamburg Energized is responsible for t ... Open whole case

BCG Questions

Solved 27.8k times
BCG Questions What arouses your interest when you are working / studying / doing another activity (from the CV)? Tell me of a time where you had no idea what you were doing. When did you use an uncommon approach to do something? Have you ever had responsibility for other people? Tell me of a situation where you were not the official leader.
4.5 5 213
| Rating: (4.5 / 5.0) |
Difficulty: Intermediate | Style: Fit Interview | Topics: Personal fit

What arouses your interest when you are working / studying / doing another activity (from the CV)? Tell me of a time where you had no idea what you were doing. When did you use an uncommon approach to do something? Have you ever had responsibility for other people? Tell me of a situation where ... Open whole case